Construction Updates

 
Update for March 1, 2008
Here is the summary of ongoing and upcoming events. Electrical inspection failed because of egress lights issue. The corrective work on egress lights has been completed and electrical inspection is scheduled for Monday. Elevator passed final inspection. Cleaning is in...

Update for February 18, 2008
Here is summary of the work done last week and the upcoming events for the construction project. Final Plumbing inspection passed. Electrical work was completed and electrical inspection for the inside of the building passed. Outside egress lights need to...

Update for February 3, 2008
Alhamdolill-Allah we are at the end of our Construction for Phase II. Since my last report on 1/20/08: 1. Sprinkler system sub did show up last week and completed their work. System is activated and as such we need to...

Update for January 21, 2008
Alhamdolill-Allah we are at the end of our Construction for Phase II. However, there has been no significant progress since mid December.   The remaining issues before we can get temporary COO are: 1. Final inspections for Plumbing, Electrical, Fire...

Update for January 3, 2008
Alhamdulill-Allah we are nearing the end of our Construction for Phase II. The remaining issues before we can get temporary occupancy certificate are: Final inspections for Plumbing, Electrical, Fire alarm and Sprinkler system Roof: Parapet Fence Interior Doors All these...

Update for December 2, 2007
Alhamdolill-Allah we are nearing the end of our Construction for Phase II. In coming few weeks we intend to complete most of the remaining work and request for Temporary or Conditional Certificate Of Occupancy (COO). Major remaining item is completion...

Update for October 27, 2007
Ongoing Work: Sheetrock work is substantially complete on all floor. Second and third floor painting is complete and first floor painting is to start this week. Electrical work on first floor is complete. Audio and data wiring, acoustic ceiling and...

Update for September 30, 2007
Ongoing Work: Insulation and interior Sheetrock work is substantially complete on all floor. Third floor painting is complete and Second floor painting has started. Electrical work on first floor is complete. Audio and data wiring, acoustic ceiling and flooring work...

Update for September 4, 2007
Ongoing Work: Insulation and interior Sheetrock work is substantially complete on third and second floors and progressing well on first floor. Third floor painting has started. Electrical work on first floor is nearing completion. Audio and data wiring, acoustic...

Update for July 27, 2007
Overall Recap After months of negotiations IAR terminated its contract with the GC (RP construction Company) on Jan. 11,2007. Several different options that were under review starting Nov.2006 were evaluated in depth after termination of RP contract. A number of...

Previous Construction Updates
Update July 1, 2007

  1. EIFS (stucco) exterior work related to building is 90-95% complete.
  2. With few exceptions window frames and windows have been installed.
  3. Roofing work is complete.
  4. Sprinkler work inside the building is complete.
  5. Structural steel bracing is complete. The deficiencies in stair-cases are being corrected and once complete we expect to pass Structural steel work inspection and certification.
  6. Plumbing and electrical work are continuing.

Projections:
Time Schedule:
The building is sealed with exception of Mehrab and two other small areas. The Mehrab construction material is being modified to cut cost. A number of options are being evaluated for this. Date of completion is by the end of the year (Insha-Allah). The schedule of construction may need to be adjusted according to available financial resources. If city inspections schedule and finances work out an early date of complete is quite possible.

Cost Estimates:
No new cost data is available and as such previous cost estimate has not been revised.