Here is summary of the work done last week and the upcoming events for the construction project.
- Final Plumbing inspection passed.
- Electrical work was completed and electrical inspection for the inside of the building passed. Outside egress lights need to be modified to meet the code. The sub was apparently aware of this problem but ignored it, hoping that city will overlook it.
- Elevator is ready for final inspection.
- Cleaning is in progress.
- Sound System: Second floor sound system testing /correction postponed until after all the inspections are done.
- Side Walk: 95% complete. Grading needs to be completed soon.
- Touch ups in progress and to be completed before installation of carpet.
- HVAC dampers installed but one cover is awaited.
- Remaining door hardware continues to be installed. Existing doors to be
repaired once new door work is complete.
- Carpet installation on first floor: Monday onward.
- Fire extinguishers to be installed at sites per recommendations of fire
marshal.
Once the carpet installation is done we should be ready for final fire and fire alarm inspection. During this inspection, electrical, sprinkler and HVAC subs have to be on site. I am hoping that above work will be completed by the end of this week. The final overall building inspection is to be scheduled once we pass fire inspection and then we have to apply for temporary occupancy permit.
|