Update for January 3, 2008
Alhamdulill-Allah we are nearing the end of our Construction for Phase II.
The remaining issues before we can get temporary occupancy certificate are:
Final inspections for Plumbing, Electrical, Fire alarm and Sprinkler system
Roof: Parapet Fence
Interior Doors
All these items were scheduled for completion during last few weeks but because of holidays got delayed. Completion of these is now expected before the end of next week - January 12, 2008.
Use of Mussallah is dependant upon installation of carpet and audio system. Carpet is expected to arrive any day and audio system testing is scheduled for Jan. 14, 2008.
We thank Allah (SWT) and ask Him to reward all our brothers and sisters for their tremendous contributions and support for this project.
|