Here is the summary of ongoing and upcoming events.
- Electrical inspection failed because of egress lights issue. The
corrective work on egress lights has been completed and electrical
inspection is scheduled for Monday.
- Elevator passed final inspection.
- Cleaning is in progress.
- Sound System: Second floor sound system testing /correction is in
progress and is to be completed this week.
- Side Walk, grading and seeding is complete.
- Touch ups: completed.
- Fire Alarm inspection failed because HVAC smoke detectors were not
working properly. Corrective work is scheduled for Monday & Tuesday and
inspection is to be scheduled for later part of the week.
- Remaining door hardware has been installed. Existing doors to be repaired this week.
- Carpet installation: completed.
- Sprinkler System inspection failed because new inspector asked for some
additional work. This work is scheduled for Monday / Tuesday before its
final inspection in later part of the week.
Once the above work is completed we should be ready for final fire marshal
inspection. I am hoping that above work can be completed by the end of this
week. The final overall building inspection is to be scheduled once we pass
fire inspection and then we will apply for temporary occupancy permit.
|