Update for October 27, 2007
 
Ongoing Work:
  • Sheetrock work is substantially complete on all floor.
  • Second and third floor painting is complete and first floor painting is to start this week.
  • Electrical work on first floor is complete.
  • Audio and data wiring, acoustic ceiling and fire sprinkler work on Second and third floor is complete and in progress on first floor.
  • Lobby and prayer hall have been walled off to tie into new building.
  • Third floor flooring is substantially complete except bathrooms. Second floor flooring is to start this week.
 
Remaining Issues:
  • Conflicts with Sub for insulation of on the roof ducts for HVAC, needs to be resolved.
  • The plumber is behind the schedule.
  • Railing for stairs has been replaced but is unsatisfactory.
 
Updated Budget: No new information is available to update the cost estimates. The following is re-cap of previous reports.
 
Budget is re-estimated to be $4.2 Mil+ 100K. This includes:
  • cost over-runs.
  • Cost of Sprinkler system and
  • Cost of a number of items previously excluded from the budget.
 
However it does not include cost of:
  • Minarets and Dome.
  • Fixtures or furniture.
  • Computers and other fit up for computer lab.
  • Science lab fit up.
  • Removing trailers and re-fencing etc
 
Completion Date: A completion schedule is being prepared with the Target date for substantial completion at the end of December. Insha-Allah.
 
JAK