Update for September 30, 2007
 
Ongoing Work:
  1. Insulation and interior Sheetrock work is substantially complete on all floor.
  2. Third floor painting is complete and Second floor painting has started.
  3. Electrical work on first floor is complete.
  4. Audio and data wiring, acoustic ceiling and flooring work is in progress.
  5. Lobby has been temporarily roofed in preparation for making it available during Ramadan.
Remaining Issues:
  1. Conflicts with Sub for programming Controller for HVAC, system testing and warranty were finally resolved this week.
  2. Backflow Valve for Sprinkler System was changed to appropriate valve.
  3. Railing for stairs is to be replaced soon.
Updated Budget:
No changes for this period. The following is re-cap of previous report.
 
Budget is re-estimated to be $4.2 Mil+ 100K. This includes:
  1. cost over-runs.
  2. Cost of Sprinkler system and
  3. Cost of a number of items previously excluded from the budget.
However it does not include cost of:
  1. Minarets and Dome.
  2. Fixtures or furniture.
  3. Computers and other fit up for computer lab.
  4. Science lab fit up.
  5. Removing trailers and re-fencing etc
Completion Date:
Date for substantial completion is end of November/December Insha-Allah.