Update for September 4, 2007
 

Ongoing Work:

  1. Insulation and interior Sheetrock work is substantially complete on third and second floors and progressing well on first floor.
  2. Third floor painting has started.
  3. Electrical work on first floor is nearing completion.
  4. Audio and data wiring, acoustic ceiling and flooring work is to start in next four weeks.
  5. Lobby has been temporarily roofed in preparation for making it available during Ramadan.

Remaining Issues:

  1. Conflicts with Sub for programming Controller for HVAC, system testing and warranty are being resolved.
  2. Backflow Valve for Sprinkler System has not been resolved.
  3. Railing for stairs does not meet the code and is to be replaced.

Updated Budget:

Budget is re-estimated to be $4.2 Mil+ 100K. This includes:
  1. cost over-runs.
  2. Cost of Sprinkler system
  3. Cost of a number of items previously excluded from the budget.
However it does not include cost of:
  1. Minarets and Dome.
  2. Fixtures or furniture.
  3. Computers and other fit up for computer lab.
  4. Science lab fit up.
  5. Removing trailers and re-fencing etc

Completion Date:

Date for substantial completion is end of November/December Insha-Allah.