Update for September 4, 2007
Ongoing Work:
- Insulation and interior Sheetrock work is substantially complete on third and second floors and progressing well on first floor.
- Third floor painting has started.
- Electrical work on first floor is nearing completion.
- Audio and data wiring, acoustic ceiling and flooring work is to start in next four weeks.
- Lobby has been temporarily roofed in preparation for making it available during Ramadan.
Remaining Issues:
- Conflicts with Sub for programming Controller for HVAC, system testing and warranty are being resolved.
- Backflow Valve for Sprinkler System has not been resolved.
- Railing for stairs does not meet the code and is to be replaced.
Updated Budget:
Budget is re-estimated to be $4.2 Mil+ 100K. This includes:
- cost over-runs.
- Cost of Sprinkler system
- Cost of a number of items previously excluded from the budget.
However it does not include cost of:
- Minarets and Dome.
- Fixtures or furniture.
- Computers and other fit up for computer lab.
- Science lab fit up.
- Removing trailers and re-fencing etc
Completion Date:
Date for substantial completion is end of November/December Insha-Allah.
|
|