Construction Committee October 2, 2006 Report
Current Status
As previously reported because of back order of doorframes and windows the construction was delayed significantly. Window frames arrived today and hopefully construction can get back on track. Kitchen is to be completed by October 8,06. Masonry work is almost complete.
Upcoming plans
As previously reported, in order to have minimum disruption of the facilities during Ramadan, Mehrab side wall of existing Prayer Hall and Lobby demolition and installation of sprinkler pipes in the existing building has been delayed until after Ramadan. The new proposed schedule of construction by GC contemplating completion of construction by March 07 is still being reviewed and negotiated by P&CC.
Concerns
P&CC has been concerned about inability of the GC to properly co-ordinate different aspects of construction and subcontractor’s work. These concerns have been repeatedly communicated to the GC and have not resulted in significant improvement in his performance. GC has been warned about consequences and alternatives are being evaluated. One of the alternatives being negotiated is to have contract addendum with penalty clause for further delays.
|